Redwood Engineering & Construction will be bidding on the SF Golden Gate Heights Playground & Field Renovation Project in San Francisco as a prime contractor and invites certified LBEs and others to submit a subcontractor quote.  The project bids on 03/04/2020.  Please direct proposals to 
Potential subcontractor scopes include, but aren’t limited, to the following:
- Survey
 - Synthetic Turf
 - Playground Equipment Installer
 - Certified Playground Safety Inspector
 - Trucking
 - Concrete
 - Metalwork / railing
 
The engineer's estimate is $1,286,000 with a contract duration of 245 calendar days and $2500 per day liquidated damages. Plans and specifications can be downloaded from San Francisco's website: